Consideration was given to a report of the Engineer, Highways & Engineering, Unity Partnership, which sought approval for the award of a civil engineering contract in excess of £400,000 to Bethell Construction Ltd for Delph New Road / A62 Huddersfield Road Flood Alleviation Scheme following the tender selection process.

 

The Cabinet was informed that the Gatehead and Huddersfield Road area had been identified as a local priority area for a flood risk management scheme. There was a history of flooding in the Gatehead area and along Huddersfield Road. 110 domestic properties and 43 commercial sites were

affected by flooding at Gatehead housing estate and internal flooding along Huddersfield Road. The two locations flooded approximately 1 in 10 years.

 

The project involved the procurement, tender evaluation and acceptance for Delph New Road / A62 Huddersfield Road Flood Alleviation Scheme. The works included the construction of proposed highway drainage, including pipe, manholes, gullies and the construction of an outfall structure.

 

Options/Alternatives considered:

·       Agree to appoint the preferred contractor and enable a purchase order for the works value to be raised for the works associated with Delph New Road / A62 Huddersfield Road Flood Alleviation Scheme.

·       Do not agree to appoint the preferred contractor to undertake the works.

 

RESOLVED that – the Cabinet would consider the commercially sensitive information contained at Item 14 of the agenda.

Publication date: 20/08/2019

Date of decision: 19/08/2019

Decided at meeting: 19/08/2019 - Cabinet